PROGRESS UPDATE – MILEWATER HOUSING FOR CONNSWATER HOMES

Phase 1 of this scheme (comprising 19 of the 49 homes) is nearing completion, with a scheduled handover date of 16 November 2021 – some 10months ahead of the original contract programme!
C&F’s site team, headed up by Site Manager, Oliver McLernon has been instrumental in driving the ongoing success of this high quality scheme – well done to all involved! This has been coupled with our collaborative and progressive working relationship with Connswater Homes and their representatives, the Boyd Partnership.